Stock code

300693

100MW/200MWh Utility Project

The 200MW/400MWh energy storage power station in Kaiyang County is located in Shuangliu Town, Guiyang City. It is one of the 15 optimally configured independent energy storage demonstration projects within Guizhou Province, and the first centralized energy storage power station in Guiyang City. As a part of Guizhou Province's 2023 independent energy storage demonstration projects, it effectively guarantees a high-quality, safe, reliable, and highly efficient power supply for the local area, while playing a crucial supporting role in building a modern energy system in Guizhou.



Working Around the Clock, Going All Out

The SINEXCEL on-site energy storage team strictly executed their plans with seamless coordination. They completed the preliminary wiring, individual unit commissioning, and overall system commissioning in just 7 days. Within 10 hours, they rapidly achieved everything from the 35kV grid-connection test to full-capacity grid-tied operation, collaborating with the client to deliver the project on schedule, efficiently, and to a high standard.


Black Start Capability, Commissioning-Friendly

The energy storage products are equipped with a complete black start function. Before the site is connected to the grid, a black start can be initiated simply by using the DC power output from the battery system. This allows for back-to-back power testing both on and off the grid, which significantly shortens the commissioning cycle and facilitates rapid grid connection for the project.


Modular Multi-Branch, Stable Operation

Each Power Conversion System (PCS) contains 10 power modules. By utilizing the pioneering modular multi-branch technology, it provides one-to-one charge and discharge management for the 10 battery clusters within a single 3.44MWh battery cabin. In this project, a total of 580 PCS modules independently manage 580 battery clusters. This solves the "weakest link" effect (barrel effect) and circulating current issues, significantly improving overall battery utilization.


Deployment
2023
Location
Guiyang, Guizhou, China
Capacity
100MW/200MWh
Product
29*3450K PCS + 2*1725kW PCS
Empower Energy Freedom
Keep it simple, make it flexible, and retain use of energy stable
Contact Us
  • The Solutions or Products You are interested in*
  • SINEXCEL is the controller and is responsible for your personal data. Our Privacy Notice describes your various data protection rights and how you can exercise them. These rights SINEXCEL is the controller and is responsible for your personal data. Our Privacy Notice describes your various data protection rights and how you can exercise them. These rights apply to any of your information that we process, and include the right to access, receive a copy of, or request the deletion or correction of your information. In some cases, you may object to the further processing of your information. Where Sinexcel has asked for your consent to process your information, you may withdraw that consent at any time.For more details about our privacy practices and your rights, please see our full Privacy Notice.

    For more details about how we use personal data and on data privacy rights, please visit our full Privacy Notice.
    See more
  • Please enter a First Name
    Close
    Submission successful
    Stock code
    300693.SZ
    0755-8651-1588 sales@sinexcel.com